Facts
What EPCOR Wants You to Know About EPCOR's Plans in Rossdale

What You Really Need to Know About EPCOR's Plans in Rossdale
This information circular by EPCOR was released just days before the Alberta
Energy and Utilities Board's hearings into the application for this project.
The ethics of such timing are most questionable. In addition, this release is
so misleading in many areas that it may, in fact, be in violation of the Alberta
Fair Trade Practises Act and the Federal Competition Act. Consider the following
claims in the circular:
- "Renovation" - This project is described as a "renovation". It involves
the demolition of a large historically and architecturally significant building
and the eventual construction of three monstrous buildings in its place. It
will see the output of the Rossdale site rise from around 220 megawatts today
to around 750 megawatts eventually. The Rossdale plant will go from a "peaking"
plant (that is, one that is operated only occasionally during peak demand)
to one that is operated on a continuous basis. Total power generated at the
Rossdale site will eventually be around ten times the current level. One meteorologist
has claimed that emissions from the Rossdale site will eventually be greater
than the emissions from all the traffic in Edmonton. This is an EXPANSION
not a RENOVATION.
- "It would cost over a billion dollars and would mean a significant rate
increase for consumers" - EPCOR's circular indicates that the cost of
decommissioning the Rossdale facility would be "billions of dollars". This
ignores the results of the study by Coopers and Lybrand that was commissioned
by Edmonton Power in 1988. That study estimated that the costs associated
with shutdown of the Rossdale Power Station and the rehabilitation of the
site was around $9.8 million. Edmonton Power (now known as EPCOR) at that
time applied for, and received, a rate increase to allow the accumulation
of a $9.8 million fund to cover those costs. A large portion of that fund
has now been accumulated and hence the net cost to decommission the Rossdale
generating station and rehabilitate the site would be close to zero. When
challenged on the "billions of dollars" claim at the EUB Hearing on April
17, EPCOR admitted this number was incorrect.
- "Smaller" - The circular talks about this being "smaller". Phase
I of this project will increase capacity of the Rossdale site from 211 megawatts
today to 391 megawatts by the addition of a new 170 megawatt gas turbine generator.
Phases II and III will see the capacity ultimately increased to around 750
megawatts. This is LARGER not SMALLER.
ConCerv wishes to make the following comments on the EPCOR "commitments" contained
in the circular shown above. The numbers below are from the circular above.
- EPCOR will not be working within their existing site perimeters. They intend
to take over the Emergency Response Department (ERD) site and have that rezoned
from "Parkland" to "Public Utility" or "Industrial". This will allow EPCOR
to expand onto that site in addition to their existing area and this will
continue the trend of "creeping expansion" that has been occurring on the
Rossdale site since 1912.
- It is unlikely that anything of historical significance can be retained
within the scope of the three expansions to occur on the Rossdale site. The
historically and architecturally significant Maxwell Dewar Building will be
demolished even though Alberta Community Development has asked EPCOR to consider
those options which would allow it to be retained. The recently discovered
Palisade Wall that was shared by the two trading companies will have to be
excavated for the foundations for the new buildings. And access to the balance
of the site will be denied as it will be within EPCOR's security area. This
is a tragedy as the Rossdale site is one of the most historically significant
areas in Canada. To name just a few of the more important features:
- This is where Sir Wilfred Laurier proclaimed the Province of Alberta
in 1905.
- This is one of the few places in Canada where the North West Company
and the Hudson's Bay Company shared a common site.
- This was the site of the first permanent European settlement west of
the Red River in Winnipeg.
- Recent artefacts found on the EPCOR site date back 8000 years. This
confirms that the Rossdale area has been a gathering place for First Nations
People for millennia
- The archaeologically significant areas lie within the security perimeter
of the EPCOR site and no public access will be possible. It is difficult to
understand how these artefacts can be preserved for future generations if
public access is not permitted.
- The existence of First Nations and European gravesites on the Rossdale
site has been known for a long time. Maps of the first settlements of the
area clearly show their boundaries. First Nations People raised the issue
at EPCOR's Annual General Meeting in 1999 and were promised then that the
matter would be resolved. Yet despite this, EPCOR officials continue to deny
the existence of gravesites in the area of the project and have done little
to resolve the concerns of First Nations People on the matter. It is difficult
to see how these concerns can be accommodated within the scope of the proposed
expansion projects.
- The physical appearance of the Rossdale site could have been improved at
any time over the last 100 years and does not require this expansion project
to allow site improvements to be undertaken. Unfortunately, EPCOR has not
placed any importance on aesthetics, and the appearance of the current site
is nothing short of abysmal. This is the view that all visitors to Edmonton
see as they come down Queen Elizabeth Drive into the City. It is difficult
to understand how anyone could claim that an industrial site such as Rossdale
could be compatible with the Downtown Park System and the Legislature and
its grounds.
- The efficiency of the Rossdale units will be improved with the RD11 project.
However, it will still leave Rossdale as one of the most inefficient power
stations in the Province.
- EPCOR are to be commended for their consideration of Edmonton in this project.
Unfortunately, the power from this expansion is not really required. Readers
are referred to the web page of the Power Pool at www.powerpool.ca to obtain
the most up-to-date statistics on the supply and demand for power in Alberta.
This shows the following:
| |
1997 |
1998 |
1999 |
2000 |
2003 (est.) |
| Available Power (Megawatts) |
8344 |
8713 |
8780 |
9396 |
10,000+ |
| Peak Demand (Megawatts) |
6659 |
6778 |
6812 |
6934 |
7500 |
Although there is sufficient power overall in the Province, there is a problem
in the location of that power generating capacity. The overwhelming bulk of
the power generation capacity is in the north of the Province while the large
growth in recent years has been in the south. If left uncorrected, this imbalance
will have a serious effect on load stability, transmission losses, and overall
costs to all Albertans. The Rossdale expansion will do nothing to help this
situation. In fact, it could even make it worse.
- EPCOR's claim that it has been a good corporate citizen in Rossdale is without
foundation. EPCOR has turned its Rossdale site into a construction site for
most of the last 10 years with only scant concern for their Rossdale neighbours.
The three phases of expansion at Rossdale will turn it into a construction
site for the next 10 years. Undertakings given in the 1988 Environmental Impact
Study are still waiting to be commenced. Noise levels remain above acceptable
limits in a number of areas. And so on. EPCOR, in fact, has been a very poor
corporate neighbour and this has been communicated on many occasions to EPCOR
Management. The most recent of these was at a meeting with senior EPCOR management
on April 5, 2000. Despite being told this news on numerous occasions, EPCOR
claims they are fine corporate citizens and this project enjoys significant
local support. The reality is that this project enjoys little or no support
in Rossdale (or in Edmonton for that matter) and the wishes and requests of
Rossdale residents have been totally ignored on a consistent basis.
Alberta's Power Supply
"...over the next few years we will see significant generation facilities
built here. You'll see the price driven downward."
- Sean McGoldrick, Vice-President, Technical Services for ESBI Alberta Ltd.,
the electricity Transmission Administrator1
There is not an impending electrical shortfall. System Reserve Capacity is
Growing. Since 1998, electrical energy supply in Alberta has been tight. But
this is changing quickly - by next year reserve will be ample. The timing of
generation additions relative to the load growth on the Alberta Interconnected
Electrical System (the "Grid") is the key to having an appropriate level of
reserve capacity. Recall a few years ago, with the completion of Genesee - it
was claimed that the system was grossly oversupplied.

Recently, reserve margins have been tight, but with the expansion of the BC
tie and new generation now being completed, ample reserve will be in place by
mid 2000.
EPCOR continues to proclaim that there is an urgent need for new generation.
But independent industry experts disagree. A Power Pool of Alberta spokesperson
has stated that plants with a combined total of 1,018 megawatts are scheduled
to come on stream.

Some points to keep in mind:
- Peak electrical load on the Alberta interconnected system is 7000 megawatts.
Generation capacity on the system is close to 8000 megawatts.
- Approximately 1000 megawatts of generation will come on-stream by 2000.
- Price sensitive load is about 500 megawatts. This is curtailed through price
during peak demand periods when there is insufficient reserve.
- Load growth in Alberta has been about 3% per year. Growth to 7500 megawatts
by the year 2000 would represent a growth rate of 3.5% per year.
- The capacity of the BC tie has been increased from 400 megawatts to 950
megawatts.
- The net contribution coming to the City of Edmonton from the revenues due
to this expansion might be in the order of $3 million per year*. Those revenues
could be generated by installing this capacity at another site. They need
not be lost just because Rossdale is not expanded.
- EPCOR's proposal claims to provide 140,000 person years of construction
employment. This amounts to 35 jobs over two years.
- There is no compelling economic reason for locating this additional capacity
at Rossdale.
Quality of life is our City's most important economic advantage. The river
valley ranks as #1 on every survey asking Edmontonians what they like most about
their City. The Rossdale site occupies a most remarkable piece of land. It is
not surprising that Edmontonians want to reclaim this site.
No information is presented as to what this represents as a return to EPCOR's
shareholders after costs and taxes are paid. However, based on EPCOR's total
revenues paid to the City as a percentage of all revenues, it is estimated that
the return to the City from the power generated by this expansion might be $3
million per year. That amounts to about $4 per citizen per year.
This revenue does not have to be lost if Rossdale is not expanded. Generating
capacity equivalent to that of Rossdale could be installed elsewhere at a comparable
site at a comparable cost. There is no compelling reason for constructing this
new capacity at Rossdale. There is no "Rossdale Advantage". Construction of
this new capacity elsewhere would allow EPCOR to continue to capture those revenues.
There are other locations where EPCOR could locate this additional capacity
either as combined cycle power or, preferably, as co-generation. EPCOR does
not give any evidence it has pursued additional co-generation options (e.g.,
in combination with an industrial user). Such a unit would have an efficiency
of up to 70% and would therefore be more economic than the Rossdale proposal
which has an efficiency of about 50%. It could be located elsewhere.
Incomplete Disclosure
Some points that EPCOR won't tell you:
- EPCOR documents make only one small reference to future plans on the site
beyond repowering unit #8 with unit #11. This is a serious omission.
- Demolishing the building is necessary only to accommodate future expansions-
repowering is just the first of several phases in the creation of a much larger
power plant than what exists or is proposed today.
- Approval of this phase 1 expansion would give rise to justification for
further expansions by retrofitting the remaining two high-pressure turbines.
- On September 9th, 1999 EPCOR officials confirmed that these further expansions
are a definite possibility. This amounts to an incomplete disclosure by EPCOR
of plans for the site.
- EPCOR makes much of the available transmission facilities at Rossdale. Other
services must be considered. A new 16" high-pressure natural gas line will
have to be run through Edmonton's south side and under the river to serve
the plant.
- The Transmission Administrator refutes that Rossdale is an ideal
location for large new generation.
- It will cost $500 million to expand the transmission system to accommodate
more electrical energy moving down the Edmonton/Calgary corridor - a cost
that will be born by all Alberta consumers.
No private company could make a proposal of this nature without full and true
disclosure. It is time EPCOR made a full and complete disclosure about intentions
for this site, and it is time there was an open discussion about options for
this site in an open forum. Not behind closed doors with Council as has occurred
in the past.
EPCOR's misreading of its community support is a result of three factors:
- Failure to ask a direct question of any significant number of people.
- Lack of clarity on the nature of the project and its long-term implications
with respect to land use.
- The presentation of "specific" messages to audiences to secure the desired
result, rather than the provision of full and open disclosure. Examples -
District Heating to downtown business groups, Smaller Building to nearby residents,
Power Shortages to citizens, Emission "Reductions" to environmental groups,
and so on. That none of these messages bears up under scrutiny is interesting
their impact in total is disturbing.
ConCerv has approached significant numbers of citizens on the valley trails,
in Rossdale and elsewhere in the city. The vast majority has not heard of the
EPCOR proposal. On one day alone, five said they wanted more information before
forming an opinion. One said that utilities are essential services. All others
- more than 180 citizens - were horrified to learn that City Council had approved
the EPCOR proposal, were strongly opposed to the project, and signed a petition
calling for City Council to:
- Reverse its approval of EPCOR's Rossdale Repowering Project.
- Adopt a long-term vision that phases out major utilities from Edmonton's
central river valley.
This sampling of public opinion, while informal, is five times greater than
EPCOR's public participation process. On the basis of 39 completed questionnaires,
most simply requesting more information, EPCOR concluded that Edmontonians support
this project. On the basis of our contact with citizens, we conclude that EPCOR's
public participation program was effective in only one respect - making this
the quietest major project in Edmonton's history.
Emissions
Air: Total hourly NOx emissions will increase.

Emissions per unit of electricity will go down, but unit #8/11 electrical output
will mor than triple. Peak ground level concentrations result from a new stck
with more dispersion. The unit will operate continuously, 50% more per operating
hour and many more hours per year.
Water: Thermal emissions to the river will increase as a result of continuous
operation.
Some points:
- EPCOR documents show that the proposed expansion could be accommodated within
the existing structure. The incremental cost is given as $3 million.
- The EPCOR documents make no mention of any development of the Rossdale site
other that the repowering of units #8 and #11.
The EPCOR documents make it clear that the proposed expansion involving Units
#8 and #11 could be accommodated within the LP Building. This could be achieved
by custom designing the gas turbine and heat recovery units and/or lowering
the foundations by ~25 feet by using soldier piles. This was confirmed by EPCOR
in the September 9, 1999 meeting with ConCerv.
In that September 9 meeting, EPCOR gave this incremental cost as $5 million,
but in its documents it gives the cost as $3 million. Regardless of which is
correct, the point is that the repowering project can be completed in a fashion
that leaves the LP Building intact.
Grant money is available from other levels of government for preservation of
such a historic building.
About the building:
- Demolition of the historic building - one of only five in Edmonton and
the only one to rate 48/48 on an historical importance valuation. This does
not represent an enhancement of the Rossdale site.
- The tallest section of the plant is currently 75 feet tall. The proposal
calls for it to be rebuilt as a structure that is 97 feet (or ten stories)
high.
- The proposal adds an additional large stack to the three currently operating.
EPCOR plans to replace the firefighters training facility with an equipment
storage yard.
According to the report on the Historical and Architectural Merit contained
in EPCOR's Municipal Environmental Impact Assessment, the Rossdale Generating
Station is the ONLY steel load-bearing skeleton with brick curtain wall industrial
building that still exists in Edmonton. It is described in the report as displaying
"a remarkable degree of preservation". It was designed by the prominent Alberta
architect, Maxwell Dewar.
The proposal calls for the new building to be a pre-engineered structure and
be finished using a red "brick-like" metal cladding. It is not an enhancement
to eliminate the only architecturally significant resource of its kind and replace
it with a fake brick metal clad structure.
EPCOR makes much of the elimination of six of the stacks. The six stacks are
those located on top of the historic building. They have not been in operation
for years and could be removed. Their proposed elimination is in conjunction
with the proposed demolition. The three larger stacks will remain and a new
larger stack will be added that will be in continuous operation.
- While district heating systems were installed at the turn of the century,
recent North American installations are not common even in locations with
higher fuel prices than Alberta.
- A future Rossdale system would lack one of the large economic drivers that
would be present in an arrangement where the electrical generation is located
with the heat sink thereby have the ability to supply electrical load without
bearing transmission and distribution costs.
- EPCOR has indicated that it has studied district heating in the 1970s,
1980s and 1990s, finding that the concept then and now is uneconomic.
With these findings it is difficult to understand why District Heating features
so prominently in EPCOR's promotional literature. It would appear that in this,
as in other cases, EPCOR's promotional literature is connected only loosely
to the factual situation or business reality.
How Efficient is the Rossdale Location?
EPCOR has said that "With generation being in close proximity to the load,
transmission losses are reduced and the efficiency of the overall system is
improved. If all of the load currently supplied from Rossdale were supplied
from Cloverbar, energy losses would increase on the order of 3-4 million kWh
per year."
To put this number in perspective, it represents about 0.4 MW or less than
0.2% of the efficiency of the Rossdale plant. By way of comparison, transmission
losses in Alberta average about 6% of all power generated and delivered to customers
over the transmission system (about 2.5 billion kWh per year). The efficiency
range of new combined cycle and co-generation projects coming on stream is from
less than 50% (Rossdale) to about 70%.
It is also important to look at location factors and efficiency from a broad
perspective. Load growth in central and northern Alberta has been substantial
but it is accompanied by excellent opportunities for co-generation. It obviously
makes sense to install co-generation at Joffre, Fort Saskatchewan and Fort McMurray
where the opportunities exist. However, this does add to the existing transmission
situation where there is much more generation in central and northern Alberta
and looming transmission constraints on the Edmonton/Calgary corridor.
High efficiency opportunities that are site-specific must be located at those
sites. The proposed Rossdale capacity is at the low end of generic combined
cycle efficiency.
New capacity of generic efficiency should be sited in consideration of the
total transmission system. Given the above factors, we conclude there is no
energy efficiency advantage to the Rossdale site.
Greenhouse gas emissions resulting from the total electrical energy used by
customers are a result of total customer demand and the efficiency with which
the demand is served including generation efficiency as well as total system
transmission and distribution losses.
Footnotes:
1. The Edmonton Journal, Wednesday 8 September 1999
revision information
$Id: facts.php,v 1.2 2004/01/18 23:30:46 tim Exp $